Friday, August 1, 2008

National Audit Office Press Notice: Ministry of Defence: Chinook Mk3 Helicopters



National Audit Office Press Notice
Ministry of Defence: Chinook Mk3 Helicopters

THIS STATEMENT IS NOT FOR PUBLICATION OR BROADCAST BEFORE 0001 HOURS ON WEDNESDAY 4TH JUNE 2008

Report by the Comptroller and Auditor General
HC 512 2007-2008
4 June 2008
ISBN: 9780102954142
Price: £7.70

The NAO has today reported on whether the Ministry of Defence has taken appropriate steps to make its fleet of eight Chinook Mk3 helicopters operational. The helicopters were delivered in 2001 but airworthiness concerns mean that they have been kept in storage and not flown operationally.

According to today’s report to Parliament, the MoD’s progress in fielding the Chinook Mk3 helicopters has been protracted. As a result, the shortage of helicopters to support operations has been exacerbated. Had the MOD been quicker to progress the ‘Fix to Field’ project (the technical solution to make the Mk3 helicopters operational), the subsequent ‘Reversion’ project (to convert them to the Mk2 standard) would have been unnecessary.

The MOD’s decision to revert the Chinook Mk3 helicopters will make them available for standard support helicopter operations two years earlier than would have been the case under the ‘Fix to Field’ project and will improve operational flexibility. The interim arrangement for special operations requirements has been achieved by adapting Chinook Mk2/2a helicopters with the Night Enhancement Package, though this has been an imperfect solution.

The operational requirement to make additional helicopters available in Afghanistan meant that the March 2007 decision to cancel ‘Fix to Field’ and revert (adapt for standard operations) the Chinook Mk3 helicopters was made quickly and not based on the level of detailed analysis that would usually be expected for an investment of this magnitude. The project did, however, subsequently pass through the Department’s regular approvals process before the main contract was placed in December 2007.

The total costs associated with the Chinook Mk3s from their initial procurement through to completion of the ‘Reversion’ project will be some £422 million not including further expenditure required to sustain the night enhancement package necessary to conduct demanding very low light missions.

Tim Burr, head of the National Audit Office, said today:

"Since 2001 the MOD has been trying to work out how to make the Chinook Mk3 helicopters available for operations. Its original Fix to Field project progressed very slowly. In 2007 changing operational imperatives meant that the Department decided to start a new reversion project to make the helicopters operational more quickly, though with a lesser capability. The Chinook Mk3 story reemphasises the importance of timely decision making, clearly understanding requirements and proceeding purposefully to the solution."

Notes for Editors:

Eight Chinook Mk3 helicopters were ordered from Boeing in 1995 as part of a larger order of Chinook Mk2a helicopters. The helicopters were delivered to the MoD in 2001. The Chinook Mk2a’s have been in use since; the Mk3’s have not, however, flown on operations, because their avionics software did not meet UK military airworthiness standards. This is despite Boeing fulfilling contractual obligations.

The Ministry of Defence subsequently began a project, called ‘Fix to Field’, to make the Mk3 helicopters operational and enable them to be used on special operations. In March 2007, the MoD decided to make the eight Mk3 Chinooks available for operations in Afghanistan as soon as possible. The Fix to Field project was therefore cancelled in favour of the ‘Reversion’ project to convert the Mk 3 helicopters to a standard similar to those in the Mk2/2a Chinook fleet.

The National Audit Office investigated the initial procurement of the Mk3 helicopters as part of the 2004 Battlefield Helicopters report.

The Committee of Public Accounts reported in 2005.

The Night Enhancement Package was fitted to modified Chinook Mk2a’s in 2002 as a short-term measure enabling them to fly in low light conditions. The Package includes items such as navigational units, thermal imagers, moving map displays and night vision goggles.

Press notices and reports are available from the date of publication on the NAO website, which is at www.nao.org.uk. Hard copies can be obtained from The Stationery Office on 0845 702 3474.

The Comptroller and Auditor General, Tim Burr, is the head of the National Audit Office which employs some 850 staff. He and the NAO are totally independent of Government. He certifies the accounts of all Government departments and a wide range of other public sector bodies; and he has statutory authority to report to Parliament on the economy, efficiency and effectiveness with which departments and other bodies have used their resources.

Press Notice 25/08



Technorati Tags:
,


No comments: